Al-Haroon, M.
Case history: Failure analysis of a syngas compressor
Gas Processing/LNG
/ Maintenance & Reliability
/ Petrochemicals
/ Process Optimization
/ Acid Gas Removal
/ Americas
/ Asia/Pacific
/ Compressors
/ Construction
/ Corrosion
/ Economics
/ Engineering & Design
/ Environment
/ Equipment
/ Europe
/ Middle East
/ Rotating Equipment
/ Safety
A first-stage impeller in a synthetic gas compressor failed after 20 years of service. The compressor is a six-stage centrifugal compressor driven by a steam turbine. This case history discusses the i..
- 1
- ... 1 pages
Current Digital Edition

Sign up to Receive Our Newsletter
Latest News
- Envision Energy powers world's first green marine ammonia bunkering 7/25
- New catalyst breakthrough could make clean ammonia easier to produce 7/25
- U.S. Gulf refiners seek Middle East, S. American oil to offset Venezuela, Mexico losses 7/25
- CEO of Russia-backed Indian refiner Nayara resigns after EU sanctions 7/25
- PetroChina makes FID for new northeast refinery complex 7/25
- Valero Energy beats Q2 profit estimates as refining margins improve 7/24
Construction Boxscore: Project Spotlight
Project:
Long Son Petrochemicals Complex
Location:
Long Son, Vietnam
Operator:
Siam Cement Group
Cost:
$5.4 B
Capacity:
1.65 MMtpy
Completion date:
2023
Status:
Under Construction